Fonterra Boiler Auxiliary Installation

 
 
< BACK
 
 

Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers. This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
Te Awamutu site - installation of steam piping and header

  • Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers.
  • This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
  • PFS manufactured and installed the new header and all interconnecting pipe work to two fire tube boilers.
  • Pipe work and installation was completed within two weeks to enable Fonterra to operate at full production levels.
  • Due to the expertise of our site services crew the manufacture of the temporary stack was expedited and loss for Fonterra was minimised.

Customer: Fonterra
Location: Te Awamutu

Fonterra Boiler Auxiliary Installation
 
 
 
 
 
 
Enquire

Fill in the form below to enquire about this service. Please make sure you fill in all required (*) fields.

Name *
 
Email Address *
 
 
Comments
 
 
 
 
 
SQL: INSERT INTO TABLE_HIT_LOG (RECORDID,PAGE,IPADDRESS,BROWSER,VERSION,LOADTIME,MEMORY,DATEADDED) VALUES ('edit5c15adce1e1de','edit4cfdacb408908','54.167.15.6','Bot','Unknown', 0.0722880363464,5308480,1544924622)
Error: Table './pfsadmin_core/TABLE_HIT_LOG' is marked as crashed and should be repaired