Projects | Dairy Yashili Pipe Bridge

Full fabrication set of drawings as well as assembly and installation were completed after design for the pipe bridge was handed over by Babbage. 

Key Features:

  • After fabrication and coating, the unit was landed in 2 completed spans in our yard.
  • Our ASME welders fitted the pipe to the bridge and Best Insulation completed the cladding.
  • Due to the 30m length of the main span, specialist transport was provided by Roach’s to Pokeno. 
  • Once on site, a twin crane lift was required to place the main span on the towers followed by the shorter roadway span.
  • Pipe ranging from 50mm SS to 300mm SS and gas, steam and, carbon pipe joined where the spans met.
  • Upon completion of QA package, a hydro was conducted to certify the completed lines.

 

 

 

Responsive
Lead-time

Responsive
Lead-time

Skilled
People

Skilled
People

Integrated Design
Capability

Integrated Design
Capability

Scale &
Capacity

Scale & Capacity

New Zealand
Owned And Operated

New Zealand
Owned And Operated

Quality
Assured

Quality
Assured

Make an Enquiry Start a conversation with our team.