Maintenance | Pulp & Paper Tasman Evaporator III

3 large pressure vessels were installed on seismic pedestals accessed by stairs and walkways to all levels with extensive Stainless and Carbon Pressure Piping. 

Key Elements:

  • 133,000 man-hours completed on the job.
  • 25T of spooled stainless and carbon piping installed.
  • 100T of structural steel.
  • 90T of product vessels installed and commissioned. 3 off.
  • Insulation of vessels along with all steam piping.
  • 80T of lamella heating elements joined and installed.
  • 9 hydro tests completed and passed.
  • 12 months duration from start to finish.

Challenges:

  • OJI procured vessels offshore along with structural support pedestals. These did not comply with NZ Seismic requirements. PFS carried out extensive stiffening bracing and upgrades to the pedestals.
  • Geotechnical issues delayed the start of the works after PFS had mobilized a large team to install spooled piping. A positive solution was reached with the team to do extensive work upgrading other parts of the plant.
  • To optimize off-site work on the free issue gear before work could commence on-site, OJI set PFS up in a large warehouse in Kawerau. This enabled PFS to expedite this work concurrently with pipe spooling in the PFS shop.

Responsive
Lead-time

Responsive
Lead-time

Skilled
People

Skilled
People

Integrated Design
Capability

Integrated Design
Capability

Scale &
Capacity

Scale & Capacity

New Zealand
Owned And Operated

New Zealand
Owned And Operated

Quality
Assured

Quality
Assured

Make an Enquiry Start a conversation with our team.