Miraka milk powder plant upgrade work.
Key Features:
- Onsite for 6 months - installed piping in existing pipe bridge and tie-in.
- Stainless & carbon pipe spool, installed and connected to steam piping - connected to new reboiler.
- Multiple services, steam, condensate, service air, instrument air, potable water.
- Moved compressed air equipment to the new compressor room.
- On-time delivery. Over 5000 manhours.
- 100% pass on all NDT site welds.
- 580 butt welds completed.
- PFS part of 4 contractor teams with great communication.
- Excellent reports from client on H&S.