Maintenance | Pulp & Paper Kinleith September Shut 2016 - 1st and 4th Effect Replacement Evaporator 5

During the September shut in 2016 we were engaged by OJI to complete the 4th effect shell and 1B lamella replacement. We had a strict deadline of 11 days to complete the work. 

Key Features:

  • 15 men 24 hours a day.
  • 400T mobile crane lifting 60T at 20m.
  • Strict health and safety requirements working amongst a turpentine plant.
  • Two Evaporator effects were worked on simultaneously.
  • Limited workspace.
  • 100% NDT on all sealing welds.
  • All weather site.