Fonterra Boiler Auxiliary Installation

 
Fonterra Boiler Auxiliary Installation

Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers. This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
Te Awamutu site - installation of steam piping and header

  • Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers.
  • This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
  • PFS manufactured and installed the new header and all interconnecting pipe work to two fire tube boilers.
  • Pipe work and installation was completed within two weeks to enable Fonterra to operate at full production levels.
  • Due to the expertise of our site services crew the manufacture of the temporary stack was expedited and loss for Fonterra was minimised.

Customer: Fonterra
Location: Te Awamutu
 
 
 
 
 
 
Enquire

Fill in the form below to enquire about this service. Please make sure you fill in all required (*) fields.

Name *
 
Email Address *
 
 
Comments