PFS Projects

 
 
MIRAKA Steam & Air Piping Upgrade

Miraka milk powder plant upgrade work By PFS included :

  • Onsite for 6 months - install piping in existing pipe bridge and tie in.
  • Stainless & carbon pipe spool, install and connect to steam piping to new reboiler.
  • Multiple services, Steam, condensate, service air, instrument air,potable water.
  • Move compressed air equipment to new compressor room
  • On time delivery.over 5000 manhours
  • 100% pass on all NDT site welds
  • 580 butt welds completed
  • PFS part of 4 contractor team with great communication
  • Excellent reports from client on H&S

    Customer: Miraka
    Location: Miraka Milk Powder Plant
    Industry: Dairy
     
     
     
  •  
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade
    MIRAKA Steam & Air Piping Upgrade